BACKGROUND
R Dependable Construction, Inc., contractor for the project, has completed the project as specified. The project was awarded to R Dependable Construction, Inc., on September 22, 2015, and the total bid amount was $199,400.00.
The project consisted of an interior ADA restroom upgrade to the facility, as well as removal of acoustic ceiling material at the Tibor Rubin and Chapman branch libraries.
The following is a financial statement for the final payment:
Original Contract Price $199,400.00
Change Orders $ 19,900.00
Total $219,300.00
Value of Work Completed $219,300.00
Less Retention ($ 10,965.00)
Total Less Retention $208,335.00
Previous Payments $208,335.00
Amount Due/Final Payment $ 10,965.00
Total Project Value To Date $219,300.00