DISCUSSION
With the Civic Center Revitalization Project Team fully assembled, a project kick-off meeting was held in October 2023, to introduce the Edgemoor Project Team, including different specialty consultants (public safety design, lighting design, park design, building system design, civil engineering design, etc.) The meeting detailed what to expect during the design development phase of the Project and desired outcome goals during the ENA period. To focus efforts, the workload and various team members were divided into five work streams (Design & Construction; Entitlements, Permitting, & Engagement; Project Financing; Commercial/Legal; Building Commissioning). Over the past six months, a significant amount of progress has been achieved. Provided is a detailed summary of the PSF activities and significant milestones to date:
Design & Construction Work Stream – Initial work focused on reviewing site conditions and preparing different massing studies. That effort was narrowed into two conceptual plans, then into the final base design. With the base design accomplished, the team worked to optimize the program and workgroup adjacencies. Working closely with the GGPD team, different program options were explored and refined. Each iteration improved work efficiency within GGPD operations and improved building layout (location of elevators, mechanical systems, technology spaces, etc.) Concurrently, building façade options were explored with a focus on achieving a “statement building”, a key design principle identified. While ongoing refinement is expected, the team feels confident in meeting the intended design principles. When the final design is complete, the process will transition to preparing construction drawings. It is estimated the construction drawings will be completed this summer. The building is currently designed at 102,300 sf and connects to a four-level parking garage.
Entitlements, Permitting & Engagement Work Stream -
Environmental Review - The City, and its consultant, Michael Baker International, prepared an Initial Study and Mitigated Negative Declaration (MND), along with an associated Mitigation Monitoring and Reporting Program (MMRP), in accordance with the California Environmental Quality Act (CEQA) to analyze the potential environmental impacts of the proposed Project. The IS/MND concludes that the proposed Project will have no, or a less than significant, impact on all relevant environmental factors, provided certain specified mitigation measures are incorporated (examples of required mitigation measures include, but are not limited to: procedures for inadvertent discovery of tribal cultural resources found during ground-disturbing activities, and preparing a construction traffic management plan). A link to the digital copy of the IS/MND and MMRP are available on the City’s project website (https://ggcity.org/civic-center) under the “Resources” tab.
In December 2023, the Planning Commission held a public hearing, received comments, and adopted Resolution No. 6075-23 approving Conditional Use Permit No. CUP-250-2023, detailing certain conditions of approval required for use of the PSF. Action was also taken for the adopted Resolution No. 6080-23 adopting the MND and MMRP.
In addition to meeting CEQA requirements, the City hired the firm Dudek (Biologist) to assist with the process of draining and removing the pond in the existing Civic Center Park. The pond removal is necessary as it is located within the new PSF footprint. Dudek completed preparation of a Wildlife Management Plan that details the approach for removal and relocation of the different species that exist in the pond. Dudek Biologists will be on-site supervising the entire wildlife removal process and to ensure proper treatment of the wildlife, and transportation of aquatic wildlife to a rescue facility. The Wildlife Management Plan is available on the City’s project website (https://ggcity.org/civic-center) under the “Resources” tab.
Community Outreach - Public engagement and community outreach is an important component of the Project. Different venues were used as touchpoints with the community to share information about the Project and seek input, especially about priorities for the re-envisioned Civic Center Park. Supporting this effort, the City contracted with Placeworks to create a holistic approach for engagement with residents and key stakeholders. Through a collaborative approach, connection with approximately 3,000 individuals within the community, including numerous online interactions was achieved. Some outreach examples include:
- June 2022: The City hosted in-person and virtual open houses, respectively, to present details of the Project and to elicit feedback.
- August 2022: The City launched an online survey to provide additional opportunities for the community to learn about the project and to share their comments and ideas.
- Spring 2023: Created Project webpage offering up to date project information (https://ggcity.org/civic-center).
- Summer 2023: City Staff presented information and gathered feedback cards at booths across multiple community events throughout the City.
- December 2023: The City hosted a Developer Open House, allowing community members to meet the development team.
- March 2024: The City hosted a Small Business Coordination Event, connecting with businesses interested in opportunities to participate in the Project with over 75 attendees.
The community response has been very positive with nearly unanimous support of the new PSF. For future park amenities, flexible programming, shade and landscaping, safety, and walking paths/trails emerged as top priorities, informing the Design team on elements to include in the redesigned Park (Attachment No. 1 provides further details on community engagement).
Project Financing Work Stream – During the ENA period, staff worked with Edgemoor to review different financing strategies. Five potential options were proposed and evaluated, including General Obligation Bonds, City issued Lease Revenue Bonds, Conduit Lease Revenue Bonds, Certificates of Participation, and Project Certificate Revenue Bonds. These evaluations were based on the cost of issuance, timeline, and the ongoing administrative requirements. To assist in the evaluation, staff engaged the City’s municipal advisor, Fieldman Rolapp & Associates, as well as its bond counsel, Stradling. After a comprehensive review, it was concluded that given the City’s strong credit rating, sufficient cash on hand, aggressive project schedule, and the current market condition, it is most cost effective to finance the Project through debt issued by the Garden Grove Public Financing Authority, in the form of lease revenue bonds.
In February 2024, the City conducted a RFP and selected Stifel Public Finance as the bond underwriter. Financing documents are progressing, and it is anticipated that the final documents including a preliminary official statement, ground lease and lease agreement, bond indenture and other related financing and legal documents will be presented to the City Council for approval in April 2024. The bonds are anticipated to be issued in early June 2024. Additional information regarding project budget is provided in the “Financial Impact” section.
Commercial/Legal Work Stream – The City and Edgemoor have agreed on terms and finalized the Project Agreement (PA), subject to Council approval (Attachment No. 2). The PA is the primary document that details responsibilities for the design, construction, and financing of the Civic Center Revitalization Project. The PA term will run for two years after the final completion of the Park, to ensure all warranties and pertinent responsibilities are met. The current master schedule anticipates the Park will be completed in May 2027. Major components of the PA include:
- Edgemoor is responsible for designing and building a new PSF, a new parking structure, and a new reconfigured Civic Center Park of approximately 2.7-acres.
- The parties agree to work collectively to finalize the project design, which is anticipated in May 2023. The final construction scope will be based on City approved construction drawings meeting all required codes pertinent to the Project.
- The PSF will be sustainable and designed and certified at “LEED Silver” or higher.
- The PSF and parking structure will function as “Essential Service Facilities” and meet standards of a category four building.
- The Project will be delivered for a guaranteed maximum price that is within the affordability limit of $152 million and subject to “open book” cost review to ensure market pricing. A budget cost review will occur after completion of construction drawings to ensure pricing is set at values based on final design.
- The City is responsible for securing financing for the project and will pay Edgemoor for its work monthly. If for any reason the PA is terminated, the City will owe Edgemoor for the value of work completed and will own all design documents, materials, improvements, etc. completed to that point.
- Construction of the project will proceed under a Project Labor Agreement with the Building Trades that prioritizes local hires.
Building Commissioning Work Stream – An important component of the Project relates to a cost-effective building mechanical system with long-term reliable operability. Edgemoor has hired a commissioning agent, Altura, to work hand in hand with the Mechanical, Electrical & Plumbing (MEP) designers (GLUMAC) throughout the Project. Their work implemented in three phases: Design, Construction, and Warranty.
During the design phase, Altura will review the design packages, specifications, and bases of design to ensure compliance with project goals, LEED requirements, and industry best practices. They will also support decision-making to ensure lifecycle costs are being considered along with all building systems decisions. They will also lead the review of Building Automated System (BAS) sequences of operation, to ensure early coordination of controls processes.
During Construction, Altura will review all MEP and BAS submittals to ensure the project requirements are met and enforced. Once the systems are installed, Altura will work with the MEP trades to ensure systems are ready to be tested and will follow testing procedures developed by Altura. They will be responsible for witnessing and documenting all testing procedures and will track all commissioning issues until resolution. After commissioning is completed, Altura will ensure all materials are delivered and provide all relevant training to City staff.
During the warranty period, Altura will continue to monitor the building in an enhanced commissioning effort. Leveraging analytics and working with key facilities stakeholders, they will continue to optimize the building performance. This will also verify the building systems quality for the enhanced commissioning LEED points and will be a key component to receiving LEED certification at a level of “LEED Silver” or higher.