| |  |  |  |  |  |  |  |  |  | Agenda Item - 4.h. City of Garden Grove
 INTER-DEPARTMENT MEMORANDUM
 
 
 | To: | Scott C. Stiles 
 
 | From: | William E. Murray 
 |  | Dept.: | City Manager 
 
 | Dept.: | Public Works 
 |  | Subject: | Reject all Bids received for the West Haven Reservoir Rehabilitation Project No. 7359 and Authorize the City Clerk to re-advertise for Bids at a future date. (Action Item) | Date: | 6/14/2016 | 
 
 | 
 |  |  |  |  |  |  |  |  |  | OBJECTIVE 
 
 To receive City Council approval to reject all bids and re-advertise for bids at a future date for the construction of the West Haven Reservoir Rehabilitation Project. | 
 |  |  |  |  |  |  |  |  |  | BACKGROUND 
 
 Staff solicited bids to construct the West Haven Reservoir Rehabilitation Project and four (4) bids, ranging from $2.6 million to $3.8 million, were received and opened by the City Clerk’s Office on May 5, 2016.  | 
 |  |  |  |  |  |  |  |  |  | DISCUSSION 
 
 Due to the significant reduction in water revenue based on the State mandated water conservation regulations, it has resulted in a shortfall of Water Funds to finance the construction of the West Haven Reservoir Rehabilitation Project.  | 
 |  |  |  |  |  |  |  |  |  | FINANCIAL IMPACT 
 
 There are no funds available at this time to complete the construction of the West Haven Rehabilitation Project.  | 
 |  |  |  |  |  |  |  |  |  | RECOMMENDATION 
 
 It is recommended that the City Council:   
    
    Reject all bids received for subject project on May 5, 2016; andAuthorize the City Clerk to re-advertise Project No. 7359 – West Haven Reservoir Rehabilitation when funding is available.
 
   By:   Rebecca Li, P.E., Associate Engineer       
 
 
 | 
 |