BACKGROUND
On March 10, 2016, the Main Street Commission reviewed and recommended approval of the MSAD budget for the FY 2016-17. Assessments will remain unchanged for FY 2016-17 and will total $26,700, with a beginning fund balance of $46,798. Expenditures are estimated to be $38,382. There are no major improvements scheduled and all maintenance activities, such as, street cleaning and landscape maintenance remain the same.
On May 24, 2016, City Council adopted Resolution Nos. 9263-16, 9264-16, and 9365-16, which in general, described the proposed improvements, directed the City Engineer to prepare and file an Engineer’s Report, and stated the intention to levy and collect assessments for FY16-17, setting the public hearing date for June 14, 2016.