Item Coversheet

Agenda Item - 5.a.


City of Garden Grove


INTER-DEPARTMENT MEMORANDUM

To:Lisa L. Kim

From:William E. Murray
Dept.:City Manager 

Dept.: Public Works 
Subject:

Approval of Amendment No. 6 to the Agreement with CT&T Concrete Paving, Inc., for on-call concrete repair and replacement. (Cost: $984,000) (Action Item)

Date:10/10/2023

OBJECTIVE

For City Council to approve Amendment No. 6 to the Agreement with CT&T Concrete Paving, Inc. (CT&T), for a one-time increase of $984,000 to the current annual contract amount of $900,000 to cover the costs of the Valley View, Belgrave, and Emerald Flood Control Channel Improvements, as approved through the Fiscal Year 2024 Budget.  

BACKGROUND

The Public Works Department retained AKM Consulting Engineers (AKM) to complete a visual inspection, prepare a condition assessment, and develop preliminary repair methods for each of the City-owned Flood Control Channels. AKM concluded their report and categorized all improvements into four (4) main areas - the two (2) areas of major concern and priority were labeled “IA” Immediate Attention, and “UA” Urgent Attention. AKM”s construction estimate totaled $6,159,459; however, Public Works was able to complete this work with an in-house contractor at approximately $5,100,000 less than the consultant’s original estimate.

DISCUSSION

On June 13, 2023, City Council approved the biennial budget, which included General Fund appropriations for the flood control channel improvements, as recommended by AKM’s assessment report. CT&T started work in July 2023, completing major structural work in September 2023. CT&T will be completing the remaining work, specifically repairs to the channel floors by the end of November 2023.

FINANCIAL IMPACT

Funding for these improvements is included in the Fiscal Year 2023-2024 Capital Improvement Plan budget.  No additional appropriation is necessary to approve the contract amendment.

RECOMMENDATION

It is recommended that the City Council:

 

  • Approve Amendment No. 6 to the Agreement with CT&T Concrete Paving, Inc., for a one-time increase of $984,000 to the current annual contract amount of $900,000, for a total of $1,884,000 to cover the costs of the Valley View, Belgrave, and Emerald Flood Control Channel Improvements; and

 

  •  Authorize the City Manager to execute Amendment No. 6 to the contract with CT&T Concrete Paving, Inc., and make minor modifications as necessary.

 

By:  Raul Leyva, Streets Maintenance Supervisor




ATTACHMENTS:
DescriptionUpload DateTypeFile Name
Amendment No. 610/3/2023Backup MaterialCT_T_Concrete_Paving_Inc_-_Amend._6.pdf