DISCUSSION
As a result of the cancellation of the contract with the lowest bidder, Jon Gilmer Construction, staff reviewed the remaining six (6) bids that were received for this project. The following is the order of bids, starting with the second lowest bidder:
2. $721,175 California Landscape & Design Inc.
3. $809,582 Rhome Profile Construction Corporation
4. $904,628 MBC Enterprises Inc.
5. $980,570 Environmental Construction Inc.
6. $999,742 MLC Constructors, Inc.
7. $1,114,257 PUB Construction Inc.
Staff is recommending that the City Council award the contract to the second lowest responsible bidder, California Landscape and Design Inc. The original bid amount from California Landscape and Design Inc. was $721,175. However, in an effort to reduce project cost, staff solicited the California Landscape and Design Inc. to provide the City with its best and final bid. Acting in good faith, California Landscape and Design Inc. was able to lower their bid to $703,780. The licenses and references for this contractor have been reviewed and verified by staff, and all other documentation is in order. Additionally, the City has previously worked with this contractor, as they were the primary contractor on the Atlantis Play Center perimeter fence upgrade. They completed the project in good standing with the City.
The major components of the project includes, installation of said playground and rubberized play surfacing, demolition and replacement of picnic shelter, demolition and replacement of perimeter pool fencing, and concrete work for new exercise equipment as well as ADA compliance paths of travel.
The anticipated contract schedule is as follows:
Award Contract – Aug 22, 2023
Begin Pre-Construction- September 19, 2023 (estimated)
Complete Construction- December 15, 2023 (estimated)