DISCUSSION
Staff solicited bids for this project pursuant to Municipal Code Section 2.52.010. Seven (7) bids were received and opened by the City Clerk's office at 11:00 a.m. on Monday, June 19, 2023. Staff reviewed the bid documents submitted by the lowest qualified contractor, Jon Gilmer Construction, with a total bid of $557,940. This bid amount is within the current project budget. The licenses and references of the contractor have been reviewed and verified by staff, and all other documentation is in order.
The major components of the project includes, installation of said playground, rubberized play surfacing, demolition and replacement of picnic shelter, demolition and replacement of perimeter pool fencing, and concrete work for new exercise equipment, as well as ADA compliance paths of travel.
The anticipated contract schedule is as follows:
Award Contract - June 27, 2023
Begin Pre-Construction- July 19, 2023 (estimated)
Complete Construction- Late Fall 2023 (estimated)