| | | | | | | | Agenda Item - 3.e.
City of Garden Grove
INTER-DEPARTMENT MEMORANDUM
To: | Scott C. Stiles
| From: | Lisa L. Kim
| Dept.: | City Manager
| Dept.: | Community and Economic Development
| Subject: | Acceptance of Project No. 01-2022 - Willowick Golf Course Storage Structure Demolition as complete. (Action Item) | Date: | 11/15/2022 |
|
| | | | | | | | OBJECTIVE
For City Council to accept Project No. 01-2022, Willowick Golf Course Storage Structure Demolition Project, as complete and authorize City Manager to execute the Notice of Completion of Public Improvement and Work. |
| | | | | | | | BACKGROUND
On August 19, 2022, a construction contract was awarded to Resource Environmental, Inc., in the amount of $34,999.99 to demolish and dispose of a free-standing structure, approximately 2,000 square feet in size that was formerly a storage structure. In addition, the work included the demolition and disposal of the wood, chain link, and concrete block wall fencing; obtaining a demolition permit; notifying South Coast AQMD; site prep and staging, utility coordination and abandonment; asbestos abatement and post inspection, dust control, notifications, labor, materials, tools, equipment, transportation, mobilization, de-mobilization, and services and coordination required to complete all components and specifications associated with this demolition project located at 3001 West 5th Street. |
| | | | | | | | DISCUSSION
The contractor, Resource Environmental Inc., has completed the demolition work in accordance with the plans, specifications, contract, and other related documents. |
| | | | | | | | FINANCIAL IMPACT
There is no impact to the General Fund. The Project was completed within the budget indicated in the contract. |
| | | | | | | | RECOMMENDATION
It is recommended that the City Council:
- Accept the Willowick Golf Course Storage Structure Demolition Project No. 01-2022 as complete;
- Authorize the City Manager to execute the Notice of Completion of Public Works Improvements and Work, and
- Authorize the Finance Director to release the retention payment when appropriate to do so.
|
ATTACHMENTS: | Description | Upload Date | Type | File Name | Notice of Completion | 11/9/2022 | Notice | City_of_Garden_Grove_-_Resource_Environmental__Inc_-_Notice_of_Completion_-_November_15__2022.doc |
|
|