Acceptance of the Notice of Completion for the B-2 Demolition Project located on the northwest corner of Harbor Boulevard and Twintree Avenue, Garden Grove.  (Action Item)

Date:7/12/2022

OBJECTIVE

For Successor Agency to accept the Project No. 022-01, B-2 Site (northwest corner) Harbor Boulevard and Twintree Avenue Site Demolition Project, as complete and authorize the Executive Director to execute the Notice of Completion of Public Improvement and Work.

BACKGROUND

The project consisted of a stormwater pollution prevention plan; mobilization; bmp/erosion/dust control; clearing and grubbing the site; removal and disposal of asphalt, concrete curb and gutter; rough grading of the site; two inches of 3/4” cmb gravel, as well other items required by the specifications for the B-2 project site located at the northwest corner of Harbor Boulevard and Twintree Avenue.

DISCUSSION

The contractor, Interior Demolition, has completed the improvements in accordance with the plans, specifications, contract, and other related documents.

FINANCIAL IMPACT

There was no impact to the General Fund. The costs for this contract were funded in accordance with the Dissolution Act and were paid through the Redevelopment Property Tax Trust Fund.

RECOMMENDATION

It is recommended that the Successor Agency:

 

  • Accept the B-2 Site (northwest corner) Harbor Boulevard and Twintree Avenue Site Demolition Project No. 022-01; and
  • Authorize the Executive Director to execute the Notice of Completion of Public Works Improvements and Work.