Item Coversheet

Agenda Item - 5.a.


City of Garden Grove


INTER-DEPARTMENT MEMORANDUM

To:Scott C. Stiles

From:William E. Murray
Dept.:City Manager 

Dept.: Public Works 
Subject:

Award a contract to All Cities Engineering, Inc., for Project CP1285000 - Alwood Avenue and Anthony Avenue Water Improvements Project. (Cost: $1,560,288) (Action Item)

Date:2/22/2022

OBJECTIVE

To recommend that the City Council award a contract to All Cities Engineering, Inc., for construction of Project No. CP1285000 - Alwood Avenue and Anthony Avenue Water Improvements Project.
BACKGROUND

The 2020 Water Master Plan has identified Alwood Avenue and Anthony Avenue Water Improvement Project as one of the fire flow deficiency projects.  This project will relieve the fire flow capacity deficiencies in the areas along Alwood Avenue from Gilbert Street to end of street, Anthony Avenue from Josephine Street to Magnolia Street, and Acacia Avenue from Josephine Street to Magnolia Street.

 

The water improvements consist of approximately 1,200 feet of 12-inch, 120 feet of 10-inch, and 3,000 feet of 8-inch diameter polyvinyl chloride (PVC) domestic water pipe. It also includes the construction of approximately 13 hydrant assemblies, 110 water service connections and 5 connections to existing water mains.  This project also requires removal and/or abandonment of the existing water main(s).

DISCUSSION

Ten (10) bids were received and opened by the City Clerk’s Office on January 13, 2022, at 11:00 a.m. (see Bid Summary Sheet).  The lowest responsive bidder is All Cities Engineering, Inc., with a total bid of $1,560,288. The licenses and references of the contractor have been reviewed and verified by staff, and all other documentation is in order.  The anticipated contract schedule is as follows:

 

          Award Contract               February 22, 2022

          Begin Construction          April 4, 2022

          Complete Construction    July 29, 2022

 

 

FINANCIAL IMPACT

There is no impact to the General Fund.  This project is included in the 2021-2022 Capital Improvement Budget, and will be financed with Water Funds, in the amount of $1,560,288.

RECOMMENDATION

It is recommended that the City Council:

 

  • Award a contract to All Cities Engineering, Inc., for $1,560,288 for the construction of Project No. CP1285000 - Alwood Avenue and Anthony Avenue Water Improvements Project; and 

 

  • Authorize the City Manager to execute the agreements on behalf of the City, and make minor modifications as appropriate.

By: Rebecca Li, Senior Civil Engineer




ATTACHMENTS:
DescriptionUpload DateTypeFile Name
Bid Summary Sheet2/8/2022Cover MemoStaffAwd_Const_AllCitiesEngineering_CP1285000_BidSummarySheet.pdf
Contract2/8/2022Cover MemoAll_Cities_Engineering_Inc._Contract.pdf