| | | | | | | | Agenda Item - 4.a.
City of Garden Grove
INTER-DEPARTMENT MEMORANDUM
To: | Scott C. Stiles
| From: | William E. Murray
| Dept.: | City Manager
| Dept.: | Public Works
| Subject: | Award a contract to Elecnor Belco Electric, Inc., for the construction of Project No. CP-1292000, Traffic Signal Installation and Modifications at Various Locations FY 21-22. (Cost: $1,276,196) (Action Item) | Date: | 2/8/2022 |
|
| | | | | | | | OBJECTIVE
For City Council to award a contract to Elecnor Belco Electric, Inc. for construction of Project No. CP-1292000, Traffic Signal Installation and Modifications at Various Locations FY 21-22. |
| | | | | | | | BACKGROUND
Project No. CP-1292000 consists of the installation of a new traffic signal at Chapman Avenue/Lamplighter Street and traffic signal modifications at Euclid Street/Stanford Avenue, Garden Grove Boulevard/Casa Linda Lane, Garden Grove Boulevard/Gilbert Street and Brookhurst Street/Stanford Avenue. The project involves installing new signal equipment, poles, cabinets, conduits, cables and vehicle video detection. As part of the improvements, striping will be modified and curb ramps will be constructed to meet ADA requirements. |
| | | | | | | | DISCUSSION
Staff solicited bids for this project pursuant to Municipal Code Section 2.50.100. Seven (7) qualified bids were received by the City Clerk's office. The bids were opened at 11:00 a.m. on January 12, 2022. The lowest qualified bidder is Elecnor Belco Electric, Inc., with a total bid of $1,276,196. This bid is within the current project budget. The licenses, references and all other documentation of the contractor have been reviewed and verified by staff, and found to be in order. This contract will comply with the City’s Community Workforce Agreement.
The anticipated contract work is as follows:
Award Contract February 8, 2022
Begin Construction (estimated) March 7, 2022
Complete Construction (estimated) October 10, 2022
|
| | | | | | | | FINANCIAL IMPACT
There is no financial impact to the General Fund. This improvement is included in the Capital Improvement budget and is funded by traffic mitigation fees and red light enforcement fees. |
| | | | | | | | RECOMMENDATION
It is recommended that the City Council:
- Award a Contract to Elecnor Belco Electric, Inc., in the amount of $1,276,196, for construction of Project No. CP-1292000, Traffic Signal Installation and Modifications at Various Locations FY 21-22; and
- Authorize the City Manager to execute the agreement and make minor modifications as appropriate thereto, on behalf of the City.
By: Ken Vu, P.E., Associate Engineer
|
ATTACHMENTS: | Description | Upload Date | Type | File Name | BID SUMMARY | 1/31/2022 | Backup Material | 2-8-22_bidsummarysheet.pdf | AGREEMENT | 1/31/2022 | Agreement | Project_CP1292000_Agreement_(1).pdf |
|
|