Item Coversheet

Agenda Item - 6.d.


City of Garden Grove


INTER-DEPARTMENT MEMORANDUM

To:Scott C. Stiles

From:William E. Murray
Dept.:City Manager 

Dept.: Public Works 
Subject:

Award of contract to General Pump Company, Inc. for Project No. 7377 - Westhaven Well No. 21 Redevelopment Project. (Cost:  $290,530) (Action Item)

Date:6/12/2018

OBJECTIVE

For the City Council to award a contract to General Pump Company, Inc. for the construction of Project No. 7377 – Westhaven Well No. 21 Redevelopment Project.

BACKGROUND

Westhaven Well No. 21 is one of thirteen wells in the City and was  originally built in 1969.  The project consists of cleaning and redeveloping the well, refurbishing the pump motor, replacing the well pump, and other redevelopment tasks.

DISCUSSION

Two (2) bids were received and opened by the City Clerk’s Office at 10:00 a.m., on April 25, 2018, (see Bid Summary Sheet).  The lowest responsive contractor is General Pump Company, Inc., with a total bid of $290,530.  This bid is within the current project budget.  The licenses and references of the contractor have been reviewed and verified by staff, and all other documentation is in order.

 

The anticipated contract schedule is as follows:

 

        Award Contract               June 12, 2018

        Begin Construction          July 9, 2018

        Complete Construction    August 20, 2018

FINANCIAL IMPACT

There is no impact to the General Fund.  This project is included in Fiscal Year 2017/18 Capital Improvement Budget, and will be financed with Water Funds in the amount of $290,530.

RECOMMENDATION

It is recommended that the City Council:

 

  • Award a contract to General Pump Company, Inc., in the amount of $290,530, for the construction of Project No. 7377 – Westhaven Well No. 21 Redevelopment Project; and

 

  • Authorize the City Manager to execute the agreement on behalf of the City, and make minor modifications as appropriate thereto.

 

 

 

By:  Rebecca Li

       Associate Engineer

 

 

 

 




ATTACHMENTS:
DescriptionUpload DateTypeFile Name
Attachment1: Bid Summary Sheet5/21/2018Backup MaterialAttachments1_BidSummarySheet.pdf
Attachment2_Location Map5/21/2018Backup MaterialAttachment2_Well_21_Location_Map_(2).pdf
Attachment3_Construction Agreement5/21/2018Backup MaterialAttorneySigned_Contract_GeneralPump.pdf