Subject:

Award of contract to Big Ben Inc., for Project No. 7401 - Water Service Line Replacement Improvement Project, Phase II.  (Cost:  $1,215,322) (Action Item)

Date:6/12/2018

OBJECTIVE

For the City Council to award a contract to Big Ben Inc. for the construction of Project No. 7401 – Water Service Line Replacement Improvement Project, Phase II.

BACKGROUND

The Water Service Line Replacement and Improvement Project – Phase II consists of 441 new replacement 1” copper water service lines and water meters, 72 sections of new replacement concrete sidewalk, concrete pads, and driveway approaches, and 7 sections of new replacement cross gutters.

 

The project will require removal and/or abandonment of existing water service lines, crack seal repair and slurry seal of asphalt, traffic control, and other appurtenant work.

DISCUSSION

Ten (10) bids were received and opened by the City Clerk’s Office at 10:00 a.m., on April 11, 2018 (see Attachment 1 - Bid Summary). The lowest responsive contractor is Big Ben Inc., with a total bid of $1,215,322.  This bid is within the current project budget.  The licenses and references of the contractor have been reviewed and verified by staff, and all other documentation is in order.

 

The anticipated contract schedule is as follows:

 

 Award contract                 June 12, 2018

 Begin construction           July 9, 2018

 Complete construction    January 15, 2018 

FINANCIAL IMPACT

There is no impact to the General Fund.  This project is included in Fiscal Year 2017-18 Capital Improvement Budget, and will be financed with Water Funds, in the amount of $1,215,322.

RECOMMENDATION

It is recommended that the City Council:

 

  • Award a contract to Big Ben Inc. for $1,215,322 for the construction of Project No. 7401 – Water Service Line Replacement Improvement Project, Phase II; and 

 

  •  Authorize the City Manager to execute the agreement on behalf of the City, and make minor modifications as appropriate thereto.

 

 

By:  Rebecca Li

       Associate Engineer 

 




ATTACHMENTS:
DescriptionUpload DateTypeFile Name
Attachment 1 - Bid Summary6/1/2018Backup MaterialAttachment1_BidSummary.pdf
Attachment 2 - LocationMap5/14/2018Backup MaterialAttachment2_LocationMap.pdf
Attachment 3 - Construction Agreement5/21/2018Backup MaterialContract_AttorneySigned.pdf